Reporting

The coordinating partner must report to Norec on activities, results and expenses after each round of exchange. The reports are usually due 5 months after the last participant have returned to his or her home country. 

Results report (E04)

Describes implemented activities and how they have contributed to the project's expected results as defined in the overall project description.

Financial report – South-North (E05a)

Financial report – South-South (E05b)

The report is based on the budget in the collaboration agreement with Norec. The report must document actual expenses compared to planned budget.

In addition, an independent audit for the project must be submitted to Norec along with the results report and the financial report.

Guidelines

Guideline to financial report (E13)